Customers track of their orders

by | Nov 17, 2021 | Homework Help

A company is developing a new app that will allow customers to track the progress of their orders. The website developers charge €10,000 for every development week and it is estimated that the design will take 10 weeks from the start of the design project to the launch of the website. Once launched, it is estimated that the new site will attract extra business that will generate profits of €5,000 per week. However, if the website is delayed by more than five weeks, the extra profit generated would reduce to €2,000 per week. How will a delay of five weeks affect the time when the design will break even in terms of cash flow?

We help you get better grades, improve your productivity and get more fun out of college!!

Get Homework Answer for this question

Free title page

Free reference page

Free formatting

Unlimited revisions

Get answer to your homework