Q.A missile manufacturer requires an electrically wired subassembly for final assembly. Annual sub assembly demand is 480 “wire bundles”;order costs are $85; carrying costs are 75% of average inventory investment; and bundles cost $1,125 each. Delivery time is known with certainty to be 21 days. Establish the optimal operating doctrine.