The Pickle construction

by | Nov 23, 2021 | Homework Help

The Pickle construction division was working on one project for the 2012 fiscal year. They use the percentage of completion revenue recognition method. Contract for new administration building Total Contract Amount$ 60,000,000 Contract Grant Date August 14, 2012 Construction Began September 1, 2012 Estimated Cost to Complete at beginning of contract$ 52,000,000 Estimated Time to Complete Project2 years As of Dec 31, 2012 Construction Costs incurred to date$ 14,140,000 Billings to date$ 19,500,000 Expected costs to complete$ 36,360,000

We help you get better grades, improve your productivity and get more fun out of college!!

Get Homework Answer for this question

Free title page

Free reference page

Free formatting

Unlimited revisions

Get answer to your homework